As part of its commitment to providing transparent accurate information, the County is providing the following information that is intended to provide a factual timeline to the community regarding when the County and Economic Development Authority (EDA) learned about interest for a proposed data center in the TOD West area and the associated non-disclosure agreements (NDAs) involving the County, EDA, and Tract. 

The sequence of events is as follows: 

  • November 2023 — The Economic Development Authority and Tract entered into an NDA concerning Tract’s interest in developing a data center campus on property in West Creek.  This agreement did not involve the Tuckahoe Technology Park site in the TOD West. This NDA was authorized by the Economic Development Authority under previous Board of Supervisors and County administration, not the current Board or the current administration. A full, non-redacted version of this 2023 NDA is available here

  • No development occurred under this November 2023 NDA and discussions with the county’s economic development staff ceased in April 2024. There was no further communication with Tract on this project.  

  • August 2025 — During the public planning process for the Technology Overlay District, the owners of TOD West reached out to county staff and asked to have their property included in the TOD area.  This land was included in subsequent maps shared with the public, the Planning Commission, and the Board of Supervisors. 


  • November 6, 2025 — Following the public process, the Board of Supervisors adopted the Technology Overlay District and the Technology Zone ordinances


  • November 17, 2025 — After the TOD was adopted, Tract contacted the County with inquiries regarding developing a portion of the TOD West property where the Tuckahoe Technology Park is now proposed. The County, the EDA, and Tract subsequently entered into a separate NDA concerning that property. A full, non-redacted version of the 2025 NDAs are available here: 2025 Economic Development Authority NDA          2025 County NDA


  • June 10, 2026 — Tract filed its pre-application for a Conditional Use Permit for the Tuckahoe Technology Park, initiating the public review process. 

As of June 17, 2026, Tract has released the County and the EDA from both agreements. As part of the County’s commitment to transparency, non-redacted copies of these NDAs are now available via this webpage. 


Jeremy Raley, Ed.D. | County Administrator

Goochland County­

P.O. Box 10

1800 Sandy Hook Road, Suite 300

Goochland, VA  23063

Cell:  (804) 310-8020

 
 
 

Recent Posts

See All
Ways to Stay Informed

Community Engagement Initiatives | Goochland County, VA - Official Website Community Engagement Initiatives | Goochland County, VA - Official Website Goochland County is furthering its community engag

 
 
 
Require a CUP for TOD Data and Distribution centers

12385 South Readers Circle Manakin Sabot, VA 23103 July 6, 2026 The Honorable Jonathan Christy, Chair The Honorable Neil Spoonhower, Vice Chair The Honorable Jonathan Lyle The Honorable Charlie Vaught

 
 
 

Comments


bottom of page